About

  • Are you open to working remotely? Yes
  • Please Enter All Locations You Are Open to Work (each line will be each city, country location)
    Australia
  • Viewed 22

About me

Education

Experience

  • 2024 - Present
    Strabag

    Commercial Manager

    Commercial Manager at SCS Railway JV.

  • 2024 - 2024
    Octavius Infrastructure Limited

    Senior Quantity Surveyor

    Commercial lead for the £10M highways scheme at New Monks Farm (Shoreham by Sea) which includes a new slip road and roundabout from the junction. This is a challenging job and is the legacy left by Buckingham Group entering administration as well as the subcontractor R&W halfway through the project. This has been let on an NEC4 Option E contract with Brighton Football Club and is due to finish in May 2024.

  • 2023 - 2024
    LB Foster

    Senior Quantity Surveyor

    Senior Quantity Surveyor responsible for a £6M tunnel fire suppression installation on an NEC Option A on the Silvertown Tunnel FFS Riverlinx project.

  • 2023 - 2023
    Glan Agua Ltd

    Managing Quantity Surveyor

    Senior QS overseeing the £33M upgrade at Crossness & Greenwich STW along with £5M upgrades at Ladymead WTW for Glan Agua as part of the AMP7 Thames Water Framework.

  • 2022 - 2023
    BAM Nuttall Ltd

    Senior Quantity Surveyor

    CP6 Framework with Network Rail in the E&P team.

  • 2022 - 2022
    MJ Church Ltd

    Senior Quantity Surveyor

    Lead commercial for installation of a new footbridge located at Michaelwood Services on the M5.

    This was a £2.7m NEC3 Option C Target Cost contract, with National Highways as the client.

  • 2021 - 2021
    Fusion JV

    Senior Commercial Manager

    Senior Commercial Manager at Fusion JV working on HS2 Area Central. Responsible for delivering the final accounts for the early enabling works across 100km from Hillingdon to Warwickshire.

  • 2019 - 2021
    MJ Church Ltd

    Quantity Surveyor

    Commercial lead on a Morgan Sindall / National Grid Visual Improvement Scheme. A project that won the 2023 Engineering, Construction & Infrastructure Project of the year award 2023. Removing a number of pylons across the Dorset countryside and installing the cables underground.

  • 2017 - 2019
    MJA Ltd

    Senior Quantity Surveyor

    2 years working at Hinkley Point C in Somerset as a Commercial Manager on the client side. This project is a £16 billion construction of a Nuclear Power Station being built by Nuclear New Build (NNB) which forms part of the EDF Group. This is under various forms of NEC3 ranging from Options A, B and C.

    Commercial Lead for MJ Church on a £16.8 million NEC3 Option A subcontract where National Grid and Morgan Sindall are removing 23 electrical towers across the Dorset countryside to restore the natural beauty of the area. These cables will then be pulled into 4 no. Trenches each measuring 9.5km in length.

    Senior Commercial Manager at Fusion JV working on HS2 Area Central. Responsible for delivering the final accounts for the early enabling works across 100km from Hillingdon to Warwickshire.

  • 2016 - 2017
    GVE Commercial Solutions Ltd

    Consultant Quantity Surveyor

    Carrying out various quantity surveyor roles such as contractor\’s adjudications, commercial support, contractual advice and NEC3 training.

    March 2017 – Current – Quantity Surveyor for A One +, a joint venture between CH2M, Colas and Costain on the highways framework for the South East, Area 4.

    July 16 – December 16 – Senior QS – CMDP (Costain MWH JV) – Lead commercial working on the Southern Water AMP6 Framework for Costain on various WTW and WWTW upgrades, ranging from £3 million to £200,000. NEC3 Option A and Option C.

    July – September 2016 – Quantity Surveyor – Colorminium – Providing commercial support on a curtain walling subcontract working for Sir Robert McAlpine on the luxury apartments at Lillie Square, Earls Court. JCT Design & Build 2011.

  • 2014 - 2016
    Walker Construction UK Ltd

    Quantity Surveyor

    May 2016 – July 2016 – Dalston Kingsland Train Station Refurbishment.
    September 2015 – July 2016 – Clapham Junction Traincare Depot.
    January 2015 – August 2015 – Strood Leisure Centre.
    October 2014 – April 2015 – Will Adams Referral Centre.
    April 2014 – September 2014 – Selhurst Train Depot.
    March 2014 – October 2014 – West Malling Forecourt Improvement.

  • 2011 - 2014
    Mott MacDonald

    Assistant Quantity Surveyor

    Whist at Mott Macdonald I covered various disciplines that were both site based and office based. These were as follows.

    Nov 2011 – Nov 2012 – Southern Water AMP 5 benchmarking and cost modelling.
    Dec 2012 – Nov 2013 – Site based at Crossness STW working for Thames Water as part of the commercial team on the £220 million upgrade. Main responsibilities were change control and reviewing subcontract packages that the contractor wished to use.
    Dec 2013 – Mar 2014 – Lead Quantity Surveyor working within SEESA at the Wimbledon Substation for the £8 million refurbishment of the existing substation responsible for all commercial issues.

  • 2008 - 2011
    Balfour Beatty Plc

    Assistant Quantity Surveyor

Skills